Pipeline Work

1. Fabrication, installation, testing & commissioning of 02 no. of 12” NB MS Seamless SCH 40 Pipeline has length of 5,400 mtr. approx. (supply of 3LPE coated MS pipes by client) including supply of LR/SR 90 deg bends duly 3LPE coated.
2. Both these pipelines will be laid / installed in one common trench as per approved drawings, having approx. length of 3,700 mtr.
3. Pipelines will be pneumatically tested for 2 bars pressure
4. Welding will be SMAW at site as per ASME codes
5. MS pipelines after welding will have MPI test or UT tests as per ASME code